Construction Progress (as of Contractor Report October 2018)

  • 96 % project completed as per Project Contractor Report October, 2018*.
  • Final stage of entrance and reception exterior glass and wall.
  • Balcony railings (75% complete of the whole tower).
  • Embedding of crown at the top of the tower and exterior lighting.
  • Connecting the water and electricity to each unit.
  • Retail – shell and core ready.

*93.1% AS PER RERA AS OF October 2018 REPORT